199th Roadway Improvements Project

199th St. from Ridgeview Road to Renner Road

The City of Spring Hill will begin a roadway improvement project on 199th St. from Ridgeview Road to Renner Road, starting mid-December. This project is part of the City’s ongoing efforts to support growth, improve traffic flow, enhance stormwater infrastructure, and beautify our community. 

The project includes constructing a new road, just north of the existing roadway. The contractor, Superior Bowen, will work in multiple phases to minimize traffic conflicts. Crews will typically work from 7 a.m. to 5 p.m., Monday through Friday, with the possibility of work on Saturdays or work past 5 p.m., as needed. No work will be scheduled on Sundays.

Scope of Work

1.21 Miles of Roadway Improvements on 199th St.
  • Two new lanes constructed to the north of the current road
  • New gutters and inlets
  • New stormwater drains
  • New sidewalks and curbs
  • A walking trail
A satellite image of 199th St. with an orange line showing Ridgeview to Renner roads.
Time Frame
December 2025 to December 2026

Location
199th St. from Ridgeview Road to Renner Road